Mahinerangi Wind Farm

Mahinerangi Wind Farm

Four of the twelve turbines at Mahinerangi Wind Farm, 2 April 2011
Location of Mahinerangi Wind Farm
Country New Zealand
Location north of Lake Mahinerangi, Otago
Coordinates
Status Operational
Construction began September 2010
Commission date March 2011 (March 2011)
Construction cost NZ$75 million[1]
Owner(s) TrustPower
Constructor(s) Downer EDi (civil)
Transfield (electrical)
Turbine information
Turbines 12
Manufacturer(s) Vestas
Model(s) V90-3MW
Rotor diameter 90 m (295 ft)
Rated wind speed 15 m/s (54 km/h; 34 mph)
Wind farm information
Type Onshore
Avg. site elevation 600–730 m (1,970–2,400 ft)
Land use Farming
Land area 17.23 km2 (6.65 sq mi)
Power generation information
Installed capacity 36 MW
Maximum capacity 200 MW
Annual generation 105 GWh (stage 1)[2]
Website
Mahinerangi - Trustpower
As of April 2011

The Mahinerangi Wind Farm is a wind farm on the north side of Lake Mahinerangi, around 50 km west of Dunedin, in Otago, New Zealand. Stage one of the wind farm, generating 36 MW, was commissioned in March 2011, and an additional 164 MW is consented to be commissioned in further stages.

The wind farm is owned and operated by generator-retailer TrustPower. It is the company's second wind farm, and the second major wind farm to be built in the South Island.

Contents

History

Resource consent was granted in 2007[3] and later confirmed after an appeal to the Environment Court.[4]

Construction of stage 1 of the wind farm, consisting of twelve turbines, began in September 2010. [5] Vestas V90-3MW turbines were chosen for the wind farm, having previously used by TrustPower for stage 3 of its Tararua Wind Farm in 2007. Turbines were shipped to Port Chalmers, and trucked through Dunedin to their final site.

The wind farm generated its first electricity on 21 February 2011, with the first two turbines being commissioned.[6] All twelve stage one turbines were completed and generating electricity by the end of March 2011.[1]

Location

The wind farm will be contained within 17.23 km2 (6.65 sq mi) of land at an elevation of 600 to 730 meters above sea level and about 50 kilometres west of Dunedin.[7] Most of the land in the proposed site is pasture grazed by sheep and cattle.[8]

Transmission

Electricity generated from Stage 1 turbines will be injected into TrustPower's nearby Deep Stream and Waipori hydro schemes. This allows the wind turbines to operate in synergy with the hydro schemes, allowing water to be preserved during off-peak times while the wind farm is generating. Electricity from Stage 1 and the hydro schemes is then injected into either Dunedin's local distribution network, or into Transpower's Halfway Bush-Balclutha-Gore 110 kV line at Berwick.

Stage 2 and beyond is too large to inject into the Waipori/Deep Stream system. Instead, it will inject into Transpower's Halfway Bush-Roxburgh 110 kV line, which passes a short distance south of the wind farm. [2]

See also

References

External links